Business Today

Delay in over 340 infra projects shows cost overruns of Rs 3.16 lakh crore

Out of 384 delayed projects, 113 projects have overall delay in the range of 1 to 12 months, 61 are delayed by 13 to 24 months, 101 reflect delay of 25 to 60 months and 109 projects show 61 months and above delay. 

twitter-logo PTI   New Delhi     Last Updated: April 14, 2019  | 13:03 IST
Delay in over 340 infra projects shows cost overruns of Rs 3.16 lakh crore
The average time overrun in these 384 delayed projects is 44.78 months.

As many as 344 infrastructure projects, each worth Rs 150 crore or more, have shown cost overruns to the tune of over Rs 3.16 lakh crore owing to delays and other reasons, a report said.

"Total original cost of implementation of the 1424 projects was Rs 18,17,469.76 crore and their anticipated completion cost is likely to be Rs 21,33,649.81 crore, which reflects overall cost overruns of Rs 3,16,180.05 crore (17.40% of original cost)," the Ministry of Statistics and Programme Implementation's latest report for December 2018 said.

The ministry monitors infrastructure projects worth Rs 150 crore and above.

Of these 1,424 projects, 344 reported cost overruns and 384 time escalation.

According to the report, the expenditure incurred on these projects till December 2018 was Rs 8,06,997.78 crore, which is 37.82 per cent of the anticipated cost of the projects.

However, it said the number of delayed projects decreases to 326 if delay is calculated on the basis of latest schedule of completion.

For 686 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of 384 delayed projects, 113 projects have overall delay in the range of 1 to 12 months, 61 are delayed by 13 to 24 months, 101 reflect delay of 25 to 60 months and 109 projects show 61 months and above delay.

The average time overrun in these 384 delayed projects is 44.78 months.

The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment.

Besides, there are other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others, the report said.

It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.

Also read: GMR Infra share price rises after Tata Group-led consortium plans to buy 40% stake in all GMR airports

Also read: Arun Jaitley says infra development, clearing backlog of defence purchases will be govt's priorities for future

Youtube
  • Print

  • COMMENT
BT-Story-Page-B.gif
A    A   A
close