443 infra projects show cost overruns of Rs 4.45 lakh crore

443 infra projects show cost overruns of Rs 4.45 lakh crore

The cost of these projects has increased due to delays and other reasons.

Advertisement
    Share:
The ministry’s January 2022 report states that out of 1,671 such projects, 443 have cost overruns, while 514 projects are delayed.The ministry’s January 2022 report states that out of 1,671 such projects, 443 have cost overruns, while 514 projects are delayed.
PTI
  • Feb 27, 2022,
  • Updated Feb 27, 2022 12:26 PM IST

The cost of 443 projects in the infrastructure sector with an expenditure of Rs 150 crore or more has increased by over Rs 4.45 lakh crore over the estimate. This information has been given in a report. The cost of these projects has increased due to delays and other reasons. The Ministry of Statistics and Program Implementation oversees infrastructure sector projects costing Rs 150 crore or more.

Advertisement

The ministry’s January 2022 report states that out of 1,671 such projects, 443 have cost overruns, while 514 projects are delayed.

  According to the report, “The original cost of implementation of these 1,671 projects was Rs 22,54,175.77 crore, which is expected to increase to Rs 26,99,651.62 crore. This shows that the cost of these projects has increased by 19.76 per cent or Rs 4,45,475.85 crore.

According to the report, Rs 13,16,293.63 crore has been spent on these projects till January 2022, which is 48.76 percent of the total estimated cost. However, the ministry says that if we look at the recent timelines for completion of projects, the number of delayed projects will come down to 381.

The report did not give information about the year of commissioning of the 881 projects.

Advertisement

The report said that out of 514 projects that are delayed, 89 projects are delayed by one month to 12 months, 113 projects are delayed by 13 to 24 months, 204 projects are delayed by 25 to 60 months and 108 projects are delayed by 61 months or more. . The average delay of these 514 projects is 46.23 months.

  The reasons for the delay in these projects are delay in land acquisition, delay in getting clearances of Environment and Forest Department and lack of infrastructure. Apart from these, due to project funding, delay in implementation of detailed engineering, changes in the prospects of projects, delay in tender process, delay in award of contracts and procurement of equipment, legal and other problems, unforeseen land changes etc. Projects have been delayed.

The cost of 443 projects in the infrastructure sector with an expenditure of Rs 150 crore or more has increased by over Rs 4.45 lakh crore over the estimate. This information has been given in a report. The cost of these projects has increased due to delays and other reasons. The Ministry of Statistics and Program Implementation oversees infrastructure sector projects costing Rs 150 crore or more.

Advertisement

The ministry’s January 2022 report states that out of 1,671 such projects, 443 have cost overruns, while 514 projects are delayed.

  According to the report, “The original cost of implementation of these 1,671 projects was Rs 22,54,175.77 crore, which is expected to increase to Rs 26,99,651.62 crore. This shows that the cost of these projects has increased by 19.76 per cent or Rs 4,45,475.85 crore.

According to the report, Rs 13,16,293.63 crore has been spent on these projects till January 2022, which is 48.76 percent of the total estimated cost. However, the ministry says that if we look at the recent timelines for completion of projects, the number of delayed projects will come down to 381.

The report did not give information about the year of commissioning of the 881 projects.

Advertisement

The report said that out of 514 projects that are delayed, 89 projects are delayed by one month to 12 months, 113 projects are delayed by 13 to 24 months, 204 projects are delayed by 25 to 60 months and 108 projects are delayed by 61 months or more. . The average delay of these 514 projects is 46.23 months.

  The reasons for the delay in these projects are delay in land acquisition, delay in getting clearances of Environment and Forest Department and lack of infrastructure. Apart from these, due to project funding, delay in implementation of detailed engineering, changes in the prospects of projects, delay in tender process, delay in award of contracts and procurement of equipment, legal and other problems, unforeseen land changes etc. Projects have been delayed.

Read more!
Advertisement