UP’s 700-km Shamli–Gorakhpur Expressway moves ahead—but what do four new NHAI tenders actually cover and when can work begin?
NHAI has invited bids for four Shamli–Gorakhpur Expressway packages totalling about 253 km. The full 700-km corridor and six-hour journey remain only plans, not an opening promise.
- Sep 15, 2026,
- Updated Sep 15, 2026 6:40 PM IST

- 1/5
The latest development is a tender invitation, not an opening date
On September 14, NHAI published construction tenders for Packages 5, 6, 7 and 8 of the planned greenfield, access-controlled Shamli–Gorakhpur corridor. Inviting bids begins contractor selection; it does not mean the road is under construction across its full length or ready for traffic.

- 2/5
The four advertised packages total 252.986 km
The official chainages produce a combined design length of 252.986 km—not merely “more than 220 km.” Package 5 covers 61.4 km, Package 6 covers 74.039 km, Package 7 covers 74.047 km and Package 8 covers 43.5 km.

- 3/5
The packages cover chainage 212.6 km to 466 km
Package 5 runs from chainage 212.600 to 274.000; Package 6 from 274.000 to 348.039; Package 7 from 348.453 to 422.500; and Package 8 from 422.500 to 466.000. The 0.414-km break between Packages 6 and 7 means the four chainages are not one perfectly continuous block.

- 4/5
Bid deadlines come before contract awards and construction
The tender list set early-November 2026 closing and opening dates for the four packages. Bids must then be evaluated and contracts awarded before work can proceed under the Hybrid Annuity Mode. No corridor-wide completion or public opening date follows automatically from the tender notice.

- 5/5
The 700-km length and six-hour trip remain planning estimates
Current reporting describes the full corridor as roughly 700 km through about 22 Uttar Pradesh districts and projects a Shamli–Gorakhpur journey of around six hours instead of about 12. Final alignment, interchanges, tolls, speed limits and actual travel time will depend on approvals, construction and operations.