Adani Power shares are up 7 per cent in the past one month and 21 per cent in the past six months. Adani Power, India’s largest private power producer, on Thursday said it has received another Letter of Award (LoA) from MP Power Management Company Ltd (MPPMCL) to supply an additional 800 MW from its upcoming ultra-supercritical thermal power project in Anuppur, Madhya Pradesh. The plant will be developed on a design, build, finance, own and operate (DBFOO) basis, with fuel sourced through coal linkage allocated under the SHAKTI policy.
The Adani group firm had earlier, on August 29, 2025, secured an LoA for 800 MW from MPPMCL, taking the total awarded capacity to 1,600 MW. Both units will be commissioned within 60 months of the appointed date, with an estimated investment of around Rs 21,000 crore in the plant and associated infrastructure. The newly awarded 800 MW will be supplied at the same tariff of Rs 5.838 per kWh as the earlier allotment, Adani Power said.