Odisha train accident: CBI arrests 3 railway employees

Odisha train accident: CBI arrests 3 railway employees

CBI arrested senior section engineer Arun Kumar Mohanta, section engineer Mohammad Amir Khan and technician Pappu Kumar under Sections 304 and 201 of CrPC

Business Today Desk
Business Today Desk
  • Updated Jul 7, 2023 8:41 PM IST
Odisha train accident: CBI arrests 3 railway employeesOdisha train tragedy: CBI arrests 3 railway employees
SUMMARY
  • The Central Bureau of Investigation (CBI) has on Friday arrested three people in connection with the Balasore train accident
  • CBI arrested senior Section engineer Arun Kumar Mohanta, section engineer Mohammad Amir Khan and technician Pappu Kumar under Sections 304 and 201 of CrPC
  • A high-level inquiry has found ''wrong signalling'' to be the main reason for the Balasore train accident and flagged ''lapses at multiple levels'' in the S&T department

The Central Bureau of Investigation (CBI) has on Friday arrested three railway employees in connection with the Balasore train accident in Odisha that left at least 290 people dead and injured more than 1,000 people during the triple train crash.

The accident took place when a passenger train hit a stationary freight train, jumped off the tracks and hit another passenger train coming from the opposite direction.

Advertisement

CBI arrested senior Section engineer Arun Kumar Mohanta, section engineer Mohammad Amir Khan and technician Pappu Kumar under Sections 304 and 201 of CrPC, the penal code sections related to culpable homicide.

The CBI, in its investigation, found that the accused railway employees were also involved in the tampering of evidence. The arrested accused will be presented in the competent court and CBI will demand custody. The Railway Board had recommended a CBI probe into the accident following which on June 6, the CBI took over the investigation.

The tragic incident of the triple train accident on June 2 involved the Chennai-bound Coromandel Express, the Howrah-bound Shalimar Express and a goods train.

A high-level inquiry has found ''wrong signalling'' to be the main reason for the Balasore train accident and flagged ''lapses at multiple levels'' in the signalling and telecommunication (S&T) department, but indicated the tragedy could have been averted if past red flags were reported.

Advertisement

The independent inquiry report submitted by the Commission of Railway Safety (CRS) to the Railway Board said notwithstanding the lapses in signalling work, remedial actions could have been taken by the S&T staff if ''repeated unusual behaviour'' of switches connecting two parallel tracks were reported to them by the station manager of Bahanaga Bazar, the spot of the accident.

The report also suggested that the non-supply of station-specific approved circuit diagram for the works to replace the electric lifting barrier at level crossing gate 94 at Bahanaga Bazar station was a ''wrong step that led to wrong wiring''.

It said that a team of field supervisors modified the wiring diagram and failed to replicate it.

The report also said that there was a similar incident on May 16, 2022 at Bankranayabaz station in Khargpur Division of South Eastern Railway, on account of wrong wiring and cable fault.

Advertisement

''Had corrective measures been taken, after this incident, to address the issue of wrong wiring the accident at BNBR would not have taken place,'' the report said.

The accident on June 2 resulted in the deaths of 292 people and over 1000 were injured.

The CRS report has also said that the initial response to such a disaster should be faster an advised the Railways to review the system of disaster-response in the zonal railways and also the coordination between the zonal railways an various disaster-response forces like NDRF and SDRF.

The report in its conclusion pointed out that the rear-collission was due to the ''lapses in the signalling-circuit-alteration'' carried out at the north signal 'goomty' in the past and during the execution of the signalling work related to the replacement of electric lifting barrier for level crossing gate 94 at the station.

''These lapses resulted in wrong signalling to the train no. 12841....resulting in the train 12841 traversing on the UP loop line, and eventual rear collision with the goods trains standing there,'' it said.

The CRS has recommended that a drive should be launched to update the completion signalling wiring diagrams, other documents and lettering of signaling circuits at site. Standard practices should be followed for carrying out signalling-modification work. It has also said that any alteration to signalling circuits should be carried out with an approved circuit diagram and in the presence of an officer.

Advertisement

It also suggested a separate team should be deployed for checking and testing of modified signalling circuits and functions before restoration and reconnection of the work.

With inputs from PTI