Representative ImageIndia's thermal power generation capacity addition programme, which was exceeding the actual targets set by the government until a few years ago, has stagnated and steeply fell in the recent years due to various issues such as land acquisition, focus on renewables and funding problems of the developers, especially in the private sector.
If the target is to add 10296.15 megawatt (MW) of thermal power in 2019-20, the actual addition until the end of September 2019 was only 3345 MW, said a Central Electricty Authority (CEA) review of progress of thermal power projects under execution in the country. Of this, 1980 MW out of a target of 6040 MW is in the Central sector powered by the NTPC, 1320 MW out of a target of 4256.15 MW by various states and just 45 MW in the private sector were added during the period. In 2017-18, the target was to add 11,366.15 MW capacity, but the actual addition was only 8,710 MW. In 2018-19, the target was reduced to 7266.15 MW, but the addition was only 5781.75 MW.